Question
A $900,000 construction contract qualifies for over-time recognition. Costs incurred to date are $200,000 against total expected costs of $500,000. Revenue recognized to date (cost-based input method) is:
Scoring
- 40% Account naming / line matching
- 40% Amount correctness
- 20% Structure / section placement
IFRS 15 — Revenue from Contracts with Customers
Apply the five steps in order: identify the contract, identify the performance obligations, determine the transaction price, allocate it to the obligations, and recognise revenue as each is satisfied. Most errors come from skipping straight to the amount without first separating the obligations.
Common mistakes
- Recognising the full contract price on delivery when a distinct service obligation is still outstanding.
- Allocating the transaction price other than on relative stand-alone selling prices.
- Recognising revenue when cash is received rather than when control transfers.
Further readingIFRS 15: the five-step model